We have had an excavator on site for the past two weeks, transferring tonnes of stone from the outfall, fish trap and the fish screen bay to the areas on land “excavated” by flood water. You can see a video of the digger extracting rocks here
Some of the stone that remains will have to be removed during summer maintenance, when river levels are lower for long periods and the inlet area is drained.
With the heavy work complete, we shall focus on tidying the site and repairing the walkways, safety handrails and monitoring/control equipment, working closely with the insurance loss adjustors.
Divers have double checked to make sure the stones that passed the turbine inlet screens via an inspection plate that was ripped off, have all been removed. We now have to re-connect the generators, that have been away for oven drying, with new bearings to provide a 12 month warranty.